Title: Authorize the County Manager to sign a letter of engagement with Developers Collaborative to undergo a preliminary cost analysis for the Administrative Building at 50 County Way
Indexes: Contract
Attachments: 1. Memo Agreement with Developers Collaborative April 2023, 2. Developers Collaborative CC Predevelopment Plan 4.26.23, 3. 23-040 - Order Developers Collaborative Predevelopment Plan 4.26.23

Title For Agenda Item:

title

Authorize the County Manager to sign a letter of engagement with Developers Collaborative to undergo a preliminary cost analysis for the Administrative Building at 50 County Way

 

.recommendation

Recommended Action:

Authorize the County Manager to enter into an agreement with the Developers Collaborative for preliminary design work on the administrative building at 50 County Way.

body

 

Background and Purpose of Request:

The purpose of this request is to allow Developers Collaborative to perform a preliminary design for the County’s new Administrative building to assess the site constraints outlined in the attached memo.

Staff Contact:                     James H. Gailey, County Manager

Presentation:                          No

 

Fiscal Impact and Source:

$63,250 - Reserve Account for Building Design

 

Effective Date if Applicable:

Final report will be delivered 2 months after the Letter Agreement is executed.