Agenda Item Request:
title
Authorize the County Manager to award bid of the Cross Insurance Arena Team Boxes Renovation to PM Construction, Inc. of Saco, Maine, in the amount of $110,084.00.
body
Background and Purpose of Request:
Requestor: Bill Trufant, Director of Facilities
The County Commissioners last fall awarded a bid for new dasher boards and glass. As part of the bench flip in the arena, concrete work needs to be done to grade and fill the voids left from the benches and penalty boxes being flipped to the opposite sides of the ice. This bid award is for the concreate work and other small detail items associated with filling those voids.
The County enlisted the help of Winston Scott Architects for overall design and plan implementation.
The project was put it out to bid and the County received two (2) bid submissions. The bid submissions
both came in under budget and included bid alternates.
PM Construction Inc. $110,084
Optimum Construction Inc. $233,468
Presentation: Yes
Funding Amount and Source: The $110,084 will be funded from the Strategic Plan Account
Effective Date if Applicable: March 29, 2024